Electrical Requirements


The Protector Echo Hood models feature internal wiring for the fluorescent lights,
fans, and control panel. All internal wiring is terminated with a simple plug in
wall cord or disconnected at the upper wiring junction box for hook-up by a
qualified electrician. The blower switch and light switch wires are part of the
control panel. Refer to Chapter 3: Getting Started and Appendix C: Protector
Echo Specifications
for the wiring diagram for proper electrical installation.

Les modèles Protector Echo capot sont équipés de câblage interne pour les
lumières, ventilateurs, et le panneau de contrôle fluorescent. Tout le câblage
interne est terminée par un simple plug en cordon de mur ou débranché à la boîte
de jonction supérieure de câblage pour le branchement par un électricien qualifié.
L'interrupteur de la soufflerie et fils de l'interrupteur de lumière font partie du
panneau de contrôle. Reportez-vous au Chapitre 3: Mise en route et l'annexe C:
Protector Echo Spécifications pour le schéma de câblage pour l'installation
électrique appropriée.

Service Line Requirements


All service lines to the filtered fume hood should be ¼ inch outside diameter,
copper (brass for natural gas), and equipped with an easily accessible shut-off
valve, should disconnection be required. If the service line pressure exceeds 40
PSI, it must be equipped with a pressure regulator to reduce the line pressure.
Please check with local codes for other requirements.

Space Requirements


The dimensions for the different models are shown in Appendix B: Protector
Echo Dimensions
.

Commissioning, Setup and Startup

Requirements


All commissioning for the Protector Echo Filtered Hood requires installation,
setup, startup and configuration of the Filtration Technology. Certifying the
Protector Echo Hood should be completed for final commissioning. Refer to
Chapter 3: Getting Started for specifics on completing commissioning.