Jacks – GE Industrial Solutions Entellisys Low Voltage Switchgear Manuel d'utilisation

Page 8

Advertising
background image

8

Fig. 2-6. Method of rolling equipment into place

7. While carefully pushing the switchgear to its final site

position, the rollers that are freed from the rear of the

switchgear are then repositioned at the forward end. This

procedure should be continued until the switchgear is in its
final location. See Fig. 2-8.

8. When the switchgear is in its final position, remove all lug

bolts holding the shipping skids to the switchgear line-up.

10. Insert the tines of the forklift at one end of the line-up, raise

slightly, and remove the loose rollers.

11. Lower the end of the gear carefully to the floor.

12. Raise the other end of the line-up slightly and remove the

remaining rollers at that end.

13. Remove shipping skid from the base of the switchgear.

Jacks

Jacks may be used in place of forklifts to raise and lower
switchgear.

1. Place a jack under the front and rear corners of one end of

the line-up.

CAUTION: Do not place jacks in any other location other than
the front and rear corners of the switchgear. Doing so may
result in serious damage to the switchgear equipment.


ATTENTION: Il ne faut pas placer de vérins en aucun endroit
autre que les coins avants et arrières du dispositif de
commutation. L’équipement peut être sérieusement
endommagé si l’on ne respecte pas cette directive.

2. Raise the switchgear evenly and just enough to position a

roller beneath the equipment. Gently lower the switchgear

onto the roller. Repeat the procedure at the opposite end

of the switchgear, raising the gear far enough to place the
appropriate number of rollers under the skids, spacing

them evenly across the width of the line-up. Gently lower

the gear onto the rollers.

3. While carefully pushing the switchgear to its final site

position, the rollers that are freed from the rear of the

switchgear are then repositioned at the forward end. This

procedure should be continued until the switchgear is in its
final location.

4. When the switchgear is in its final position, remove all lag

bolts holding the shipping skids to the switchgear line-up.

5. Place one jack at each corner, front and rear, of the

switchgear. Carefully raise the line-up evenly and remove

the rollers and the shipping skids. Evenly lower the line-up

to the floor and remove the jacks.

Advertising