Entellisys low voltage switchgear, 7 compartments for future breakers, 9 bus area – GE Industrial Solutions Entellisys Low Voltage Switchgear Manuel d'utilisation

Page 17: Busing system

Advertising
background image

Entellisys Low Voltage Switchgear

17

3-7 Compartments for Future Breakers

When specified, compartments may be supplied for future

addition of circuit breaker elements. These compartments are

fully equipped with drawout rails, primary disconnects, and
ancillary devices as required (i.e. secondary disconnects,

accessory devices, etc.) The opening in the breaker compartment

door (3), Fig. 3-13, is closed with a bolted-on steel plate (2) to deter
accidental contact with energized electrical circuits.(i.e. primary

disconnect stabs).

1. Quarter-turn latch

2. Steel plate (future breaker cubicle)

3. Future cubicle door cover

Fig. 3-12. Future breaker compartment cover (padlockable ¼ turn

latch will be provided on future breaker cubicles)

3-8 Auxiliary/Transition Sections

These sections may be provided for any one or more of several
reasons including:

• Transition to a close-coupled transformer

• Incoming cable or busway when a main breaker section is

not provided

Auxiliary sections may be 22-inch, 30-inch, or 38-inch wide as
required to accommodate the space requirements. The

compartment doors on the front of the sections are hinged and

latched in the same manner as breaker compartment doors.

Generally, transition sections will be 22-inches wide for close-

coupling to transformers.

Power company metering requirements generally require either a

38-inch or 49-inch wide auxiliary section to accommodate the
current transformers, meters, test switches, etc. as required by

their individual practices, and/or regulatory commissions.

3-9 Bus Area

The bus area, Fig. 3-13, contains the main horizontal bus and
vertical riser bus bars (1) for the particular section. The vertical

bus bars are supported at the breaker run-ins (2) which are bolted

to the molded bases (3) that form the rear wall of the breaker
compartment. The horizontal bus bars are supported by the

power connectors which are bolted to the vertical bus bars. All

bolted supports and connections are accessible from the rear for
maintenance. The bus area is fully isolated from the breaker,

instrument and auxiliary compartments by the molded bases or

glass polyester sheet.

1 Vertical riser bus

2. Run-ins to breaker compartment

3.

Molded

base

4. Run-backs from breaker compartment

5.

Short-circuit

brace

Fig. 3-13. Bus construction

Busing System

Bus bars are fully tin-plated copper with bolted joints and silver
plating is optional. The standard construction is open bus. A

barrier system (Bus compartmentation) that isolates the main and

vertical bus bars from the cable area is available as an option. All
run-backs (load-side power conductors) from the breaker

compartment to the cable termination area are covered with non-
PVC insulated tubing.

The typical arrangement is shown in Fig. 3-14.

The standard bracing is 65,000 amperes, RMS symmetrical.

Bracing for 100,000 amperes, RMS symmetrical is available as an
option.

In general, when the switchgear equipment has no more than four

sections or does not exceed 10 feet in length, it will be shipped as
one complete lineup. In such cases, the only field assembly would

be to a close-coupled transformer if, the switchgear were part of a

Load Center Unit Substation. If, because of shipping and/or
handling considerations, the equipment cannot be handled in one

3

1

2

1

3

4

2

5

Advertising