Final inspection – GE Industrial Solutions Entellisys Low Voltage Switchgear Manuel d'utilisation

Page 34

Advertising
background image

34

1. Hoist rail splice plate

2. Splice plate mounting hardware

Fig. 4-26. Switchgear shipping split front splice plate


After the sections have been aligned and bolted together, on each

shipping split section remove the bolt holding the splice plate to the

hoist runner. Retain the splice plate and remove the remaining bolts,
fig. 4-32 (2), and reinstall bolts with splice plates in place. Figure 4.28

shows a typical hoist rail splice installed.

Fig. 4-27. Switchgear shipping split rear splice plate

On the runner, there is also a splice plate held in place with two
screws, fig. 4-27 shows a typical example. After the hoist rail splices

have been installed, remove and retain the two screws holding the

runner splice. Remove the two screws that are on the other side of
the shipping split. Place the runner splice over both sections of the

shipping split and align the four mounting holes. Install the four
screws that were previously removed.

Fig. 4-28. Switchgear shipping split front hoist rail splice plate


After the splice plates have been installed, run the hoist carriage

over the assembled shipping split to check the alignment of the
hoist rail and runner. If necessary, adjust the rail and/or runner for

smooth operation of the rollers on the hoist carriage.


On seismic rated equipment, it is necessary to remove the bracket

locking the hoist dolly on the carriage before the hoist can be used,

Fig. 4-25. Replace the bracket after breaker installation or removal
is complete.


Final Inspection

Make a final inspection to see that no tools, construction materials,
or other foreign matter have been left in the switchgear equipment.





1

2

Advertising