8. Energizing the Switchgear

8-1 Before Energizing

Before switchgear is energized, a thorough final check should be

made using the following checklist: Refer to section 6-5 for

additional information.

• Breakers and other operating mechanisms exercised


• Electrical insulation resistance tested phase-to- phase

and

phase-to-ground


• Entellisys instrumentation properly connected.

• Electrically operated breakers and operating mechanisms
exercised

• Ground fault protection system tested

• Protection settings properly set and tested.


• Field wiring secured and free of live bus


• Grounding connections made

• All debris, scrap wire, etc. removed

• All covers installed, doors closed and latched

8-2 Energizing Procedures

CAUTION: Energizing switchgear for the first time is
potentially dangerous. Therefore, qualified electrical
personnel should be present when the equipment is

energized. If problems caused by damage or poor installation

practices have not been detected in the checkout procedure
described previously, serious damage can result when power
is turned on.

ATTENTION: La mise sous tension pour la première fois d’un
dispositif de commutation est un acte potentiellement
dangereux. Il faut donc que du personnel qualifié en

électricité soit présent lorsque l’équipement est mis sous

tension. Si lors de la procédure de vérification décrite
précédemment des problèmes causés par des dommages ou

de mauvaises pratiques d’installation n’ont pas été détectés,

il peut en résulter des dommages sérieux lorsque le contact
est établi.

1. There should be no load on the switchgear when it is

energized.

2. Turn off all of the downstream loads, including those such

as motor control centers and other devices which are

remote from the switchgear.

3. The equipment should be energized in sequence by

starting at the source end of the system and working

toward the load end. In other words, energize the main
devices, then the feeder devices, and then the branch-

circuit devices.

4. Turn the devices on using Entellisys HMI.