After completing the installation of the main bus splice bars, the

joint covers may be mounted and secured by a 3/8-16 nylon bolt
and polyester flat washer if the bus insulation option has been

supplied with the equipment.

5. CONNECT THE TRANSFORMER SECONDARY - The connection

of the transformer secondary to the incoming bus bars in the
transition is made using the flexible connection straps

supplied with the transformer. These connections are always

bolted joints.

The recommended torque for tightening the ½-13 bolts fastening

the transformer connection straps to the incoming bus bars is 35-40
ft-lbs.

6. INTERCONNECT ENTELLISYS CONTROL AND COMMUNICATION

WIRING - Interconnection of control wiring across shipping
splits is accomplished by connecting to terminal blocks

located in the cross-section wiring trough on top of the

equipment shown in Fig. 4-14. Ethernet cables are connected
by similarly routing them across the top of the equipment and

down the gear, between the compartment side sheets in the
section containing the network switches.

If terminal blocks are provided, each wire must be attached to the
correct point on the terminal block, following the circuit

identification number attached to each wire.

Fig. 4-14. Interconnect control wiring and Ethernet cables in the wiring trough

on top of the equipment