24

4-2 Assembly and Installation of Switchgear
Equipment

General Requirements

Before assembling or installing the switchgear equipment, all

components should be available at the site location. This will
facilitate switchgear component identification as well as

installation. The foundation should be prepared in accordance
with the instructions in Sections 4-1 and 4-2, and all embedded

conduits installed and capped.

NOTE: If rollers are to be used for movement of the
equipment to its permanent installation, it is recommended

that the shipping skid not be removed until the equipment is
placed in position over the anchor bolts.

NOTE: Au cas où l’utilisation de rouleaux s’avérerait
nécessaire afin d’apporter l’équipement à son emplacement

permanent, nous recommandons que l’emballage
d’expédition ne soit pas enlevé tant que l’équipement n’est
pas positionné au dessus des boulons d’ancrage.

If a transformer is not part of the installation, and/or the

equipment has been split for shipment, place the center section
on the foundation first. Assemble the remaining sections outward

from the center section, in each direction.

If the switchgear equipment is part of a Load Center Unit
Substation, the transformer section should be set on its pad first

in accordance with the instructions furnished with the

transformer. All remaining sections of the switchgear should then
be installed.

NOTE: Before assembling and installing the switchgear
equipment, the foundation must be absolutely level and clear

of debris to prevent damage and possible misoperation of
the switchgear equipment.

NOTE: Il faut avant de procéder à l’assemblage et à
l’installation s’assurer que la fondation soit absolument au

niveau et exempte de débris afin de prévenir des dommages
à l’équipement du dispositif de commutation.

Detailed Assembly and Installation
Instructions

The recommended procedure for installation of an indoor

switchgear or Load Center Unit Substation is as follows:

1. POSITION THE EQUIPMENT-Position the equipment or

sections of the complete equipment in their final location.

Fig. 4-4. Lifting plate location

NOTE: If the equipment line-up was split into shipping
sections, the lifting plates on corners of adjacent sections

shown in Fig. 4-4 must be removed. Failure to remove these

plates will interfere with mating adjacent sections and
prevent installation of bus splice plates, structure tie plates,
etc.

NOTE: Si l’ensemble de l’équipement a été séparé en sections
pour l’expédition, il faut que les plaques de soulèvement aux

coins des sections adjacentes montrées à la Figure 4–6
soient enlevées. L’omission d’enlever ces plaques viendra en

interférence avec les sections barres omnibus, de l’attache
de la structure des plaques, etc.

Once the lifting plates have been removed, they may be
discarded.

NOTE: In the event the lifting plates must be reassembled on
the equipment for lifting purposes, they must be moved to
locations where unused screw holes are available, generally

achieved by shifting the plate horizontally on the mounting

surface one bolt-hole from its previous location. When
remounting the lifting plates, torque the mounting bolts to 7-9
ft-lbs.

NOTE: Dans l’éventualité où les plaques de levage doivent être
réassemblées sur l’équipement à des fins de levage, elles
doivent être déménagées aux endroits où il y a des trous de

boulons inutilisés, on y arrive habituellement en décalant la

plaque horizontalement sur la surface de montage d’un trou
de boulon de son emplacement précédent. Lors du

remontage des plaques de levage, serrer les boulons
d’assemblage à un couple de 7–9 livres-pied.

NOTE: All mating sections of the equipment line-up (including
transformer, if applicable) must be securely fastened together

prior to tightening anchor bolts fastening the equipment to
the mounting surface.

Fig. 4-5. View showing method of attaching equipment to

shipping skids

NOTE: Toutes les sections se rapportant à la disposition de
l’équipement (incluant le transformateur si tel est le cas)
doivent être retenues ensembles solidement avant de

resserrer les boulons d’ancrage qui retiennent l’équipement à
la surface de montage.

2. REMOVE THE SHIPPING SKIDS-The equipment is fastened to

the shipping skids with 3/8-3 lag screws through the

equipment anchoring holes. See Fig. 4-5.

Lifting Plate