Testing & inspection, 1 general, 2 key interlocks – GE Industrial Solutions Entellisys Low Voltage Switchgear Manuel d'utilisation

Page 40: 3 breaker operation test, 4 entellisys system test kit

Advertising
background image

40

6. Testing & Inspection

6-1 General

After the equipment has been installed and all
connections made, it must be tested and inspected

before it is put in service. Although the equipment and

devices have been tested at the factory, a final field test
must be made to be sure that the equipment has been

properly installed and that all connections are correct.

WARNING: The equipment must be completely de-
energized while the tests are in progress.

ADVERTISSEMENT:

L’équipement doit être

complètement désamorcé lorsque l’on procède à des
tests.

Directions for testing Entellisys instrumentation is

provided in DEH-501 (Entellisys System User’s Manual)

and DEH-233 (Entellisys System Test Kit User’s Manual.)
The proper settings of Entellisys instrumentation are

normally determined from a complete power system

coordination study performed by the purchaser or their
consultant; therefore, the settings of these devices must

be made by the purchaser.

NOTE: The trip setting adjustment of the EntelliGuard
Messenger for each circuit breaker may be in any

position when shipped from the factory and must be

correctly positioned prior to energization of the
equipment.

NOTE: Les ajustements des réglages du disjoncteur
peuvent être en n’importe quelle position lorsque

celui-ci est expédié de l’usine et ils doivent être
positionnés correctement avant que l’équipement ne
soit mis sous tension.

The extent of the tests on the equipment as a whole will

depend on the type and function of the equipment. Tests
that should be performed, however, include circuit

breaker operation, and switchgear meggering, phasing,

and grounding checks.
High-potential tests to check the integrity of the

insulation are not necessary if the installation

instructions are carefully followed. If local codes demand
this test, or the purchaser wishes to make high-potential

tests, the voltage should not exceed 75 percent of the

IEEE factory test voltage.
For the power circuit, the IEEE factory test voltage is two

times switchgear rating plus 1,000 volts. See Table 6-1.

Potential and control power transformers must be
disconnected during high-voltage testing.

Switchgear

Voltage

Rating

ANSI

Test Voltage,

ac RMS

Field

Test Voltage,

ac RMS

600V
480V

240V

2200V
1960V

1480V

1650V
1470V

1110V

Table 6-1

6-2 Key Interlocks

After initial installation of the switchgear equipment, all

necessary interlock keys should be inserted into the

appropriate locks and all spare keys should be stored in
a location in accordance with the owner's established

procedures.

CAUTION: Refer to the key interlock schematic
included in the summary furnished with the

equipment to determine the sequence of operation

and the correct number of operating keys required.
This precaution is necessary since the improper use of
spare keys will defeat the interlocking scheme.

ATTENTION: Référez-vous au schéma des clés de
verrouillage inclus au sommaire fourni avec

l’équipement pour déterminer les séquences
d’opération et le nombre correct de clés d’opération

requises. Cette précaution est nécessaire étant donné

qu’un mauvais usage des clés de réserve rendra
inopérant le programme de verrouillage.

6-3 Breaker Operation Test

All compartments housing EntelliGuard circuit breakers

have a TEST position in which the breaker primary

contacts are disconnected while the secondary contacts
are still engaged. This TEST position permits complete

testing of the electrical control circuit without energizing

the primary power circuit. When the breaker is first put
into service, its control circuit must be thoroughly tested

while in this position to make sure that all closing and

tripping circuits are complete and functioning properly.

The TEST position is not suitable for inspection and
maintenance of the breaker and should therefore be

used only for testing breaker operation.


Refer to the appropriate breaker instruction manual for

other pre-operational checks on the breakers. See DEH-

41526.

6-4 Entellisys System Test Kit

An Entellisys System Test Kit is required for testing
Entellisys Low Voltage Switchgear functionality. The

system test kit user manual is DEH-233.

6-5 Final Steps to Be Taken Before
Energizing Equipment

The following steps should be taken before energizing
the equipment:

1. Manually exercise all switches, circuit breakers,

and other operating mechanisms to make certain

they are properly aligned and operate freely.


2. Conduct an electrical insulation resistance test to

make sure the switchgear is free from short

circuits and grounds. This should be done both
phase-to-ground and phase-to-phase with the

switches or circuit breakers both opened and

Advertising