Entellisys Low Voltage Switchgear

41

closed. This test should be performed with a

1000 volt megger. Disconnect all control circuits

before checking resistance.

3. Check for secure mounting and wiring connections

at Entellisys instrumentation.

4. Using the Entellisys HMI, exercise all

EntelliGuard breakers to determine all

devices work correctly. See DEH-501 for

instructions on using the Entellisys HMI.

5. Test all protection functions using the

Entellisys System Test Kit. See DEH-233 for

instructions.

6. Make certain that field wiring is clear of live

bus and, where necessary, physically

secured to withstand the effects of fault

currents.

7. Check to determine that all grounding

connections are made properly.

8. Remove all debris, scrap wire, etc., from the

switchgear interior before closing the

enclosure.

9.

Install covers, close doors, and make certain

that no wires are pinched and that all

enclosure parts are properly aligned and

tightened.