Add, Configure, Monitor, and Replace CIP Safety I/O

5. Verify that the Network Status (NS) status indicator is alternating

red/green on the correct module before clicking Yes on the confirmation
dialog box to set the SNN and accept the replacement module.

6. Follow your company-prescribed procedures to functionally test the

replaced I/O module and system and to authorize the system for use.

Scenario 2 - Replacement Module SNN is Different from Original and Safety Signature Exists

1. Remove the old I/O module and install the new module.

2. Right-click your POINT Guard I/O module and choose Properties.

3. Click the Safety tab.

4. Click Reset Ownership.

5. Click OK.

6. Right-click your controller and choose Properties.