Installation & Servicing Instructions Rinnai Q-Series

7

2

Regulations and guidelines

The installation must comply to the requirements of the authority having jurisdiction
or, in the absence of such requirements, to the latest edition of the National Fuel Gas
Code, ANSI Z223.1/NFPA 54. In Canada, installation must be in accordance with
the requirements of CAN/CSA B149.1, Natural Gas and Propane Installation Code.

Where required by the authority having jurisdiction, the installation must comply to
the Standard for Controls and Safety Devices for Automatically Fired Boilers, ANSI/
ASME CSD-1.

Install CO detectors per local regulations. Boiler requires an inspection every 2 years
and maintenance every 4 years or 4000 hours. See maintenance section chapter 14.

Operating Limits of the boiler:

Max. boiler temperature: 176 °F (80 °C)

Max. operating pressure: 45 psi (3 bar)

Max Allowable Working Temperature ASME: 200 °F (93 °C)

Max. Allowable Working Pressure ASME: 45 psi (3 bar)

The hot water distribution system must comply with all applicable codes and
regulations. When replacing an existing boiler, it is important to check the condition
of the entire hot water distribution system to ensure safe operation.