14 maintenance, 6 installing the casing, 2 inspection – Rinnai Q130SN Manuel d'utilisation

Page 60

Advertising
background image

Installation & Servicing Instructions Rinnai Q-Series

60

13.6 Installing the casing

- Install the airbox and close all snap locks. See figure 29;

-

Install the metal casing on the boiler;

- lock the casing by using the screw behind the door. See figure 30.

14

Maintenance

Maintenance or changes to the boiler may only be carried out by a qualified

technician.

14.1 Periodic examination of venting systems and boiler

The inspection of the boiler and venting system should be done every 2 years and full

maintenance every 4 years or 4000 hours of operation, whichever occurs first. When
doing this the circumstances of the boiler’s location must be taken into account. From
this one can determine whether to deviate from this advice.

Please contact Rinnai for further guidance on the frequency and service

requirements. Contact details can be found on the back page of this manual.

14.2 Inspection

Preparing the boiler for inspection

To carry out the inspection and maintenance activities please follow the next procedure:

- switch off the power supply;

- shut off the gas;

- remove the screw behind the door on the front of the casing (figure 31);

- Lift the casing and remove it towards the front;

- valve off the boiler from the system using the boiler isolation valves in the plumbing

kit.

NOTICE

i

NOTICE

i

Removing casing figure 31

Installing casing

figure 30

2

3

1

2

3

1

2

3

1

Installing air box

figure 29

CLOSE

1

2

Advertising