The condensate trap may be primed by filling the CONDENSATE

U-ASSEMBLY with tap water while the water heater is not operating.

The system is fully primed when the water level reaches the adaptor

connected into the Tee. In most installations the water heater will self-

prime the condensate trap during the first full heat-up cycle. If a sound

of air bubbling through water (gurgling) is heard while the blower is

operating after the first heat-up cycle, then turn the unit off and contact

your plumber or service representative.

If these instructions are not followed, the condensate build-up

will block the exhaust outlet, which will cause improper operation.

Do

NOT

block or

plug any

hole in this

hex plug.

DRAIN LINE

CONDENSATE

U-ASSEMBLY,

AKA. VENT PIPE

ASSEMBLY #1

*NO PORTION OF THE FIELD SUPPLIED DRAIN LINE BEYOND

THE 1/2" ADAPTOR MAY BE ELEVATED HIGHER THAN THE

ADAPTOR. THIS MUST BE TRUE FOR THE ENTIRE LENGTH

OF DRAIN LINE INCLUDING EXIT INTO AN APPROPRIATE DRAIN.

APPROXIMATELY

0.25" (0.64 cm)

fIGure 16.

Condensate is likely to form in the venting system attached to

this water heater. The vent pipe should be sloped downward

away from the blower assembly (not less than 1/8” (3.2 mm)

nor greater than 1/2” (12.7 mm) per foot (30 cm) maximum). If

the vent piping is vented level or sloped upwards away from the

blower assembly, then adequate means for draining and disposing

of the condensate needs to be made by the installer. Two 3/8”

condensate hoses should be connected to the built in drain ports

of blower outlet adaptor. If a VAA is installed, a 3/8” condensate

hose should be connected to the barb fitting on it; otherwise the

unused barb fitting on vent pipe assembly #2 should be plugged

with one of the break-away plugs. See Figure 17.

Condensate neutralizer kits are available. Contact your distributor

or Service Agency.

Blower asseMBlY InstallatIon

1. This power vented water heater comes with blower assembly

installed.

2. After unit is set in place, make sure blower assembly is still mounted

securely. Also make sure both drain ports of rubber boot vent adapter

are capped off. Lastly, make sure there is no damage to blower.

3. Condensate drains from three locations on blower assembly. See

Figure 17. One flexible hose runs from bottom of blower housing;

two run from the ports of rubber connector at the outlet of blower.

All these three condensate hoses are connected to barb fittings at

vent pipe assembly #2. The hose from bottom of blower housing is

clamped by two clamps and the two hoses from rubber connector

are harnessed by another clamp. Make sure there is no kink or twist.

fIGure 17.

4. Make sure there is no packing material in the inlet or discharge

of the blower.

5. Make sure that the plastic tubing is still attached from the air

pressure switch to the port on the blower housing. Make sure

the plastic tubing is not folded anywhere between the pressure

switch and the blower housing.

6. Make sure the ON/OFF switch is in the OFF position and that

the outer harness is connected from the blower control box to

the connector on the bottom side of the gas valve.

7. If the outer harness is not factory installed, make sure the ON/

OFF switch is in the OFF position and then connect the outer

harness from the blower control box to the connector on the

bottom side of the gas valve.

8. Do not plug in power cord until vent system is completely

installed. The Power Vent operates on 110-120 Vac. therefore

a grounded outlet must be within reach of the 6 foot (1.8 m)

flexible power cord supplied with the vent (See Figure 1). The

power cord supplied may be used on a unit only where local

codes permit. If local codes do not permit use of flexible power

supply cord:

A. Make sure the unit is unplugged from the wall outlet. Remove

the plastic top cap. Remove screws and open panel on the

front of the control box on the blower.

B. Cut the flexible power cord, leaving enough to be able to

make connections. Remove the strain relief fitting from the

box.

C. Install a suitable conduit fitting inside the enclosure.
D. Splice field wiring into existing wiring using code authorized

method (wire nuts, etc).

E. Be certain that neutral and line connections are not reversed

when making these connections (proper polarity).

F. Ground heater properly. This water heater must be grounded

in accordance with the Canadian Electrical Code C22.1 and/

or local codes. These must be followed in all cases.

The water heater must be connected to a grounded metal,

permanent wiring system; or an equipment grounding

conductor must be run with the circuit conductors and

connected to the equipment grounding terminal or lead on

the water heater, see Figure 19.

G. Close the panel on the control box. Make sure that the access

panel is secured shut.

9. The blower discharge boot is made to accept only straight

sections of 2” pipe. To start off with an elbow, a short section

of the furnished pipe, a minimum of 2 inches (5.1 cm), must be

cut and glued into the end of the elbow that will mount on the

discharge boot.

vent terMInal InstallatIon, sIdewall

1. Install the vent terminal by using the cover plate as a template to

mark the hole for the vent pipe to pass through the wall. BEWARE

OF CONCEALED WIRING AND PIPING INSIDE THE WALL.

2. If the Vent Terminal is being installed on outside of a finished

wall, it may be easier to mark both the inside and outside wall.