AKD-20 Low Voltage Switchgear

Chapter 4. Equipment Installation

45

©2012 General Electric All Rights Reserved

The hoist should be lifted into position on top of the switchgear so
that the end with two rollers is toward the rear of the equipment,
Fig. 4-28.

Fig. 4-28. Location of hoist rear rollers


The rear wheels can then be hooked under the channel and the
front wheels can be positioned on the front track. See Fig. 4-29. The
runner guide at the rear should then be reassembled, Fig. 4-30.
Stop blocks are provided at each end of the front track to prevent
the hoist from rolling off the ends of the track.

Fig. 4-29. Front rollers positioned on front track

Fig. 4-30. Replacing the runner guide after completion of

hoist installation

Fig. 4-31. Removing the bracket locking the hoist dolly


If the equipment has been shipped in sections, fig. 4-32, there are
splice plates for the runner guide and hoist rail attached to each
respective part.