AKD-20 Low Voltage Switchgear
Chapter 4. Equipment Installation

34

©2012 General Electric All Rights Reserved

Figure 4-9 illustrates the installation of the through-bolts. The

through-bolts are in the front and rear compartments. The nut and

bolt assembly should be tightened with a torque of 25-30 ft-lbs.

Fig. 4-9. Through-bolt installation

All of the hardware required for assembling the equipment across

the shipping splits is furnished with the equipment. If a transformer

is included in the line-up of equipment, the transformer flange

should be aligned with the opening in the side of the transition

section and fastened together using the 3/8-16 bolts, nuts and

washers supplied with switchgear. The fastener assembly should

be tightened with a torque of 25-30 ft-lbs.

4. COMPLETE THE ELECTRICAL INTERCONNECTIONS - After

completing the mechanical connections between the several

sections of equipment, the electrical interconnections should

be completed. This includes the installation of splice plates

for the main bus bars, the neutral bus, and the ground bus in

addition to the control and metering circuits.


WARNING: All switchgear equipment must be adequately

grounded for safety. Failure to ground equipment properly may

result in serious injury.
ADVERTISSEMENT: Tout l’équipement du dispositif de

commutation doit être mis à la terre adéquatement de manière

sécutaire. Des blessures sérieuses peuvent survenir si l’on omet

de mettre l’équipement à la terre correctement.

Figure 4-10 illustrates the general location of the buses that must

be spliced across the shipping splits.

Fig. 4-10. Typical location of buses at shipping split