recessed steel channels be installed to support the switch-gear.

The floor channel sills under the front, center, and rear of the

switchgear base should be embedded in a level concrete slab with

their top surfaces flush with the finished floor.

While the equipment base center channel is not anchored to the

foundation, it is still required that the center channel sill (see Fig. 4-4)

be level with the foundation and also with the front and rear

channel sills to prevent structural distortion of the switchgear

equipment.

Only four anchor bolts are normally used for outdoor enclosures.

NOTE: The factory must be consulted for anchoring

recommendations for equipment subject to operational and/or

environmental (seismic) shock loading.

NOTE: Si l’équipement doit être assujetti à une charge de choc

opérationnelle ou environnementale (sismique), il faut consulter

le manufacturier afin d’obtenir des recommandations d’ancrage.

Anchor bolts and channels are to be provided by the purchaser; the

clamp plates (Fig. 4-5) are supplied with the equipment.

It is recommended that the anchor bolts be 5/8-inch diameter.

Fig. 4-5. Outdoor enclosure clamp plate

4-2 Assembly and Installation of
Switchgear Equipment

General Requirements

Before assembling or installing the switchgear equipment, all

components should be available at the site location. This will

facilitate switchgear component identification as well as

installation. The foundation should be prepared in accordance with

the instructions in Sections 4-1 and 4-2, and all embedded conduits

installed and capped.

NOTE: If rollers are to be used for movement of the equipment

to its permanent installation, it is recommended that the

shipping skid not be removed until the equipment is placed in

position over the anchor bolts.

NOTE: Au cas où l’utilisation de rouleaux s’avérerait nécessaire

afin d’apporter l’équipement à son emplacement permanent,

nous recommandons que l’emballage d’expédition ne soit pas

enlevé tant que l’équipement n’est pas positionné au dessus

des boulons d’ancrage.

If a transformer is not part of the installation, and/or the equipment

has been split for shipment, place the center section on the

foundation first. Assemble the remaining sections outward from the

center section, in each direction.

If the switchgear equipment is part of a Load Center Unit

Substation, the transformer section should be set on its pad first in

accordance with the instructions furnished with the transformer. All

remaining sections of the switchgear should then be installed.

NOTE: Before assembling and installing the switchgear

equipment, the foundation must be absolutely level and clear of

debris to prevent damage and possible misoperation of the

switchgear equipment.

NOTE: Il faut avant de procéder à l’assemblage et à l’installation

s’assurer que la fondation soit absolument au niveau et

exempte de débris afin de prévenir des dommages à

l’équipement du dispositif de commutation.

Detailed Assembly and Installation
Instructions

Indoor Equipment

The recommended procedure for installation of an indoor

switchgear or Load Center Unit Substation is as follows:

1. POSITION THE EQUIPMENT-Position the equipment or sections

of the complete equipment in their final location.

Fig. 4-6. Lifting plate location

Lifting Plate

Advertising