Chapter 4. Equipment Installation

42

©2012 General Electric All Rights Reserved

Outdoor Equipment

Outdoor equipment are anchored after re-assembly of the

separately shipped sections. The four anchor bolts should be

tightened with a torque of 45-55 ft-lbs.

CAUTION: If the equipment is to be subjected to operational or

environmental (seismic) shock loading, the factory must be

consulted for anchoring recommendations.

ATTENTION: Si l’équipement doit être assujetti à une charge de

choc opérationnelle ou environnementale (sismique), il faut

consulter le manufacturier afin d’obtenir des recommandations

d’ancrage.

Busway Connections

Busway runs must be aligned with openings in the equipment and

connected to the mating components electrically and mechanically.

A collar is mounted on the top of the equipment cable compartment

to which is bolted the busway housing. See Fig. 4-22. The 1/4-20

NC bolts, washers, and nuts for this mechanical connection are

supplied with the busway stub. The bolts should be tightened with

a torque of 7-9 ft-lbs.

Fig. 4-22. Spectra Series™ Busway mounting (front-entry)

The power conductors in the busway stub are designed to bolt

directly to power connector blocks mounted on the switchgear riser

bus bars. These connections are made with 1/2-13

NC bolts

supplied with the switchgear equipment.

NOTE: To maintain the minimum contact resistance across

bolted bus joints, it is recommended that the joint contact

surfaces be coated with a film of GE lubricating grease D6A15A2.

A can of this grease is supplied with the equipment. Do not put

grease on the bolt threads as this will affect the clamping force

exerted by the bolt.

NOTE: Afin de maintenir une résistance de contact minimale à

travers les joints vissés des barres omnibus, nous

recommandons que les surfaces du joint de contact soient

unduites d’une pellicule de graisse lubrifiante GE D6A15A2.

L’équipement est fourni avec une boîte de cette graisse. Il ne faut

pas graisser les fils des boulons car la force de serrage exercée

par le boulon en sera affectée.

The recommended torque for tightening the 1/2-13 NC bolts

connecting the busway stub connections to the riser bus power

connectors is 35-40 ft-lbs.

Control Wire Connections

For external control wiring, refer to Fig. 4-23 for switchgear cable

area dimensions, and connect the control wires to the switchgear

section as follows:

1. When control conduits enter the switchgear from below, they

should not extend more than one inch above the floor. The

control wires may be pulled through the conduits before or

after the switchgear is installed.


2. Route the control wires from the conduits through the wiring

trough (cross-hatched area- 2" x 7"-shown on Fig. 4-23) at the

side of the cable compartment. Connect the cables to the

terminal blocks in accordance with the connection diagrams

for the equipment.


3. If the control conduits enter from above, drill the top cover

within the available space indicated. See Fig. 4-23. Control

wires should be routed to the wiring trough and connected to

the terminal blocks as described previously.