4.02 Start-Up Sequence

1. Connect system to primary input power.

2. Turn ON/OFF switch to ON (up) position.

AC Indicator

turns ON after about 5 seconds.

POWER

ON

OFF

O

I

OFF

O

Art # A-04812

3. Check the AC indicator. If indicator is ON, system is ready to operate (pending fault checks by internal cir-

cuitry). If indicator does not light after a few seconds check that each inverter is correctly configured for the
input voltage and all 3 phases are present. Check Status Indicator for any codes that can help determine
problem.