GE Industrial Solutions Evolution Switchboards Manuel d'utilisation

Page 8

Advertising
background image

EEvvoolluuttiioonn SSeerriieess™

™ SSw

wiittcchhbbooaarrddss

Chapter 2- Installing the Switchboard

88

FFiigguurree 99.. Typical single-source ground-fault protection

using ground-fault relays.

FFiigguurree 1100. Typical single-source ground-fault protection

using integral ground-fault trips.

FFuussee SSeelleeccttiioonn

Select the proper fuses for each circuit based on load

characteristics and available short-circuit current at the line

terminals of the switchboard. Select a fuse for which the

rating of the combination fuse and switch equals or exceeds

the available short-circuit current. Removable link-type

fuses are not recommended.

TTeessttiinngg aanndd IInnssppeeccttiioonn
After the equipment has been installed and all connections

made, test and inspect the switchboard

before energizing.

Although the equipment and devices have been inspected

at the factory, perform a final field test to be certain that the

equipment has been properly installed and that all

connections are correct and have not loosened during

transportation. Completely check the wires and all bolts and

terminals for tightness. Check all Kirk key interlocking

schemes to insure desired performance. Make sure that the

incoming line is de-energized while all tests are in progress.
In addition to these mechanical checks, use a

megohmmeter to test the switchboard. Open all

switchboard devices and remove all instrumentation and

control fuses. Use a megohmmeter developing 500 volts.

Switchboards tested when leaving the factory show typical

minimum values of 100 megohms. If any switchboard tested

under the above conditions shows resistance values

considerably below this, inspect it for possible tracking on

insulation or insulation breakdown.
All scraps of wire, plaster, dust, and other foreign material

must be removed. Vacuum cleaning is recommended for

cleaning.
After thorough cleaning and inspection, if the megohm

reading is still low, it may still be safe to energize the

equipment. When restoring flooded or wet equipment to

service, for example, the accepted practice is to require a

minimum of

1 megohm before energizing. Under damp or

humid conditions, it is considered good practice to operate

the equipment at lower-than-rated voltage for a short time,

if possible, to improve the low reading.
Instructions for inspection and testing of low-voltage power

circuit breakers are given in the applicable individual

instruction manuals. Directions for testing devices such as

relays, instruments, and meters are found in the instruction

manual furnished with each device. Protective relays must

be coordinated with other relays in the system; therefore,

these relays are set by the purchaser. General instructions

on setting relays are provided in the relay instruction

manuals.

G

Grroouunndd--FFaauulltt PPrrootteeccttiioonn
When ground-fault protection is provided, all field

connections must be made correctly to insure proper

functioning of the ground-fault protection system. Observe

the rules described in the following sections, as illustrated in

Figures 9 and 10.

Advertising