GE Industrial Solutions Evolution Switchboards Manuel d'utilisation

Page 6

Advertising
background image

EEvvoolluuttiioonn SSeerriieess™

™ SSw

wiittcchhbbooaarrddss

Chapter 2- Installing the Switchboard

66

BBeeffoorree IInnssttaallllaattiioonn
Before any installation work is performed, study all drawings

furnished by the supplier for the particular installation. These

include arrangement drawings (front, end, and plan views),

connections diagrams, and schedule of equipment. Any

material external to the equipment that may be required to

meet any local codes (such as mats, screens, or railings) is

not furnished.

LLooccaattiioonn
When locating the switchboard, check all applicable codes

for aisle, working space, and placement requirements. The

space at the front must be sufficient to allow the doors to be

opened and removable breakers to be removed.

CClleeaarraannccee
We recommend a clearance of one inch between the back

and sides of the switchboard and the wall or obstruction.

However, this clearance is not required unless a 30 kVA or

larger transformer is integral to the switchboard.

RReeaarr AAcccceessss
Some switchboards may require access to field wiring

terminals from the rear. Do not install these switchboards

against a back wall.

FFoouunnddaattiioonn RReeqquuiirreem

meennttss

IInnddoooorr EEqquuiippm

meenntt

The floor or foundation must be strong enough to prevent

sagging from the weight of the switchboard structure. If the

foundation is subject to vibrations, the equipment must be

specially mounted to prevent transmitting vibrations to the

equipment.
The switchboard must be bolted directly to the floor, as

shown in Figure 3. The floor must be level without any high

spots that might cause misalignment. If the floor is not level,

use floor channels.

N

NO

OTTEE:: For seismically certified equipment, refer

to the installation instructions on page 5.

If steel floor channels are used, embed them in a level

concrete slab, with the top surface of the channels flush

with the finished floor. To avoid distortion of the structure,

the steel channels must be level and aligned with each other

before the equipment is anchored. The recommended

foundation construction and method of mounting the

switchboard to the foundation are shown in Figure 4.

Channels should be grouted after installation.

O

Ouuttddoooorr EEqquuiippm

meenntt

Outdoor equipment is usually installed on a level, smooth

concrete pad. When optional channel sills are supplied with

the switchboard, set them on the pad and fill them with

grout, as shown in Figure 5.

CCoonndduuiittss
When the foundation channels are being installed, any

conduits or sleeves required for power and control cables

that are to enter the equipment from underneath should be

located and installed within the available space shown on

the floor-plan drawings. Consider installing conduits or

sleeves that might be required for future connections.

Conduit stubs should extend above the floor enough to

prevent water entering. Also consider the locations of

components in the switchboard and allow space for

swinging cables after they leave the conduit. The lowest live

metal part in the switchboard will be approximately 8 inches

above the bottom of the switchboard (not including floor

sills). Note that the switchboard must be lifted over the

conduit stubs. Terminate the conduits at the switchboard

with the appropriate conduit connectors. Conduits may

require grounding or electrical connection to the

switchboard enclosure.

FFiigguurree 33.. Switchboard bolted to the floor – indoor

construction.

FFiigguurree 44.. Switchboard mounted on floor channels – indoor

construction.

Front

Advertising