Installation

8

Oven Assembly

FOLDING CONVEYOR
The folding conveyor assembly must be installed

from the control box side of the oven.
1. Unfold the right side of the conveyor.
2. Push the conveyor into the support tracks.

See Figure 6.

Be careful to avoid hitting the

red emergency off switch on the side of the

control box.

3. Unfold the left side of the conveyor and contin-

ue to push into the support tracks.

4. Insert the conveyor in beyond the normal rest-

ing position.

5. Install the drive chain around the drive motor

sprocket and the conveyor sprocket. See

Figure 7.
NOTE: Figure 7 shown without chain guard

and control box cover for clarity.

6. Pull the conveyor back out of the oven until the

1/4-20 thumb screw can be installed through

the conveyor support and into the control box.

See Figure 8.

NOTE: If the mounting hole cannot be lined up or

the chain is too loose, the drive motor will

need to be repositioned.