GE Industrial Solutions Spectra Series Switchboards Tableaux de contrôle Manuel d'utilisation

Page 11

Advertising
background image

Spectra Series™ Switchboards / Tableaux de contrôle Spectra Series™

Chapter 2 – Installing the Switchboard / Chapitre 2 – Installation du tableau de contrôle

5

Seismically Certified Equipment

For seismically certified switchboards of IBC 2006 & IEEE-

693-2005, follow the previous instructions with the

following modifications. Locate the seismic kit shipped

with each section before installation. The kit for each

section is located in the rear of the switchboard section

attached to the horizontal bus. The kit should contain

four 1-inch spacers per section. These spacers should be

installed as shown in Figure 6 or Figure 7. When floor

channels are used, these spacers should be installed as

shown in Figure 8.

Figure 6. Installation of seismically certified switchboards without

floor sills.

Figure 7. Alternate installation of seismically certified switchboards

without floor sills.

Figure 8. Installation of seismically certified switchboards with floor

sills.

Équipement sismiquement certifié

Pour les tableaux sismiquement certifiés de IBC 2006 &

IEEE-693-2005, suivre les instructions ci-dessus avec les

modifications qui suivent. Localiser le kit sismique envoyé

avec chaque section avant l’installation. Pour chaque

section le kit est localisé à l’arrière de la section du tableau

de contrôle attaché à la barre omnibus horizontale. Le kit

devrait contenir 4 espaceurs de 1-pouce par section. Ces

espaceurs devraient être installés comme montré à la

Figure 6 ou la Figure 7. Lorsque des profilés de planchers

sont utilisés, ces espaceurs devraient être installés comme

montré à la Figure 8.

Figure 6. Installation de tableaux de contrôle sismiquement certifiés

avec des seuils de planchers.

Figure 7. Installation optionnelle de tableaux de contrôle

sismiquement certifiées sans seuils pour planchers.