10.0 Commissioning Procedure

1. l Fill and vent the system.

l

Open all valves fully and vent air from the heat exchanger.

l

Check for leaks at pipe connections.

2. l Refit the outer casing and secure with the 2 screws.

l

Switch on the electrical supply.

l

Check the operation of the unit by following the operating

instructions.

3. l Set up the installation parameters on the controls system

as necessary.

l

When installation and commissioning are complete, hand

over the instruction manual to the end user.