Electrical Connections

Before attempting the electrical connection, the rating

plate should be checked to ensure that the unit’s electrical

characteristics and the supply electrical characteristics agree.

Installation of the wiring must be made in accordance with

U.L. 197 Commercial Electric cooking Appliance Standards,

Local and/or National electrical Code, ANSI/NFPA 70-1990.

1. Switch panel size

2. Overload protection

3. Wire type

4. Wire size

5. Temperature limitations of the wires

6. Method of connection (Cable, Conduit, etc)

The service line will enter through the rear of the unit and is

to be connected to the terminal block (see diagram left). The

terminal block is accessed by removing the lower front cover.

Removal of the body side is not necessary.

Input voltage and phasing must match the units voltage

and phasing . Wiring diagram is attached to the main back of

each oven. Visually check all electrical connections. Energize

electric service to units. The range is wired standard for three

phase connections. If it is necessary to change to single

phase, please refer to wiring diagram attached to the rear of

the oven. Service and unit voltage must agree.

Power Failure

In the event of a power failure, no attempt should be made

to operate this oven.