Re-Configuration Process
Events in which you have to “Re-configure”
Installing or commissioning a GFH for the first time
Replacing a fan board or a complete fan box
Replacing an Electro/Acid Sensor
Replacing a solvent sensor
Replacing a RFID board
Replacing a CPU board
Replacing a complete control module
Sash sensor failure
Hardware Configuration mismatch 9A alarm
Before beginning, you will need to have the following:
Green Fume Hood Settings sheet (example provided on next page)
6ft Ladder
Any tools needed for removal of front panel
Some white out, or a small sticker to mark the round RFID tags that are on
the primary filters only (the primary filters are the lower ones that are in
between the lights & fan box)
Piece of paper and a pen
Maintenance card
The User card that is used to operate the hood you are going to re-configure
- Protecto Ech Filtered Fume Hoods 183 Series 6' Protecto Ech Filtered Fume Hoods 183 Series 5' Protecto Ech Filtered Fume Hoods 183 Series 4 Protecto Ech Filtered Fume Hoods 182 Series 8' Protecto Ech Filtered Fume Hoods 182 Series 6' Protecto Ech Filtered Fume Hoods 182 Series 5' Protecto Ech Filtered Fume Hoods 182 Series 4' Protecto Ech Filtered Fume Hoods 181 Series 8' Protecto Ech Filtered Fume Hoods 181 Series 6' Protecto Ech Filtered Fume Hoods 181 Series 5' Protecto Ech Filtered Fume Hoods 181 Series 4' Protecto Ech Filtered Fume Hoods 180 Series 8' Protecto Ech Filtered Fume Hoods 180 Series 6' Protecto Ech Filtered Fume Hoods 180 Series 5' Protecto Ech Filtered Fume Hoods 180 Series 4'