4.01 Introduction

This section provides a description of the Power Supply
operating controls and procedures. Identification of the
Front and Rear Panel components is followed by operat-
ing procedures.

4.02 Operating Controls

This subsection provides specific functional descriptions
of the Power Supply operating controls and indicators.

A. Front and Access Panel

1.

Control Panel

All operator controls, except gas pressure adjust-
ment, are located on this panel and include:

• Power ON/OFF and RUN/SET switches

• CURRENT control

• Indicators for AC Power, TEMP, GAS/Cool-

ant, and DC.

A-02866

1

2

3

4

5

Figure 4-1 Front and Access Panels

2.

Access Panel

A panel to gain access to the bulkhead area con-
taining the torch connections.

3.

Torch Leads Input

Rubber Boot and hole in the front panel to feed
the torch leads through to the internal bulkhead
connections.

4.

Work Cable and Ring Lug

Work cable with ring lug (factory installed).

5.

Lifting Eye

Used to lift the Power Supply with cable and hook.

B. Control Panel

1.

Current Control

Adjustment to set the desired output current be-
tween 30-120 amps. The unit has an automatic
fold-back circuit that limits current to 35 amps if
torch tip contacts the workpiece.

2.

ON/OFF Power Switch

ON position supplies AC power to activate all sys-
tem control circuits. OFF position deactivates con-
trol circuits.

SET

RUN

ON

OFF

TEMP

AC

GAS

DC

A

120

30

75

50

100

CURRENT

1

2

3

4

5

6

7

A-02078

Figure 4-2 Control Panel

3.

RUN/SET Switch

RUN position is used for torch operation. SET po-
sition used for setting gas pressure and purging
lines.