Figure 6-2 Dimensions
6.1 - Mounting the
boiler
Refer to Figure 6-1:
1. place the cardboard template,
provided with the boiler, against the
wall;
2. ensure that the template is plumb
and the screw holes line up with the
wall studs;
WARNING!!!
The wall
bracket screws must be
screwed into the buildings
framing or other material
capable of supporting the
weight of the boiler or the
boiler and building may be
damaged causing severe
personal injury, death, or
substantial property damage.
3. mark the screw holes for the wall
bracket, “A”;
4. remove the cardboard template;
5. install the wall bracket “A”, using
the screws “E”, provided;
6. hang the boiler on the wall bracket,
“A”, by hanging connections “B”
and “C” on tabs “D”.
6 - INSTALLATION - Mounting the boiler
1 = Area for power supply cable
2 = Heating supply connection (3/4”)
3 = Domestic hot water connection (3/4”) (absent on 160-B model)
4 = Gas connection (3/4”)
5 = Domestic cold water connection (3/4”) (absent on 160-B model)
6 = heating return connection (3/4”)
7 = positions for boiler support
8 = Flue discharge/air intake connection
Figure 6-1 Wall bracket installation