ARC MASTER 175 SE INSTALLATION

INSTALLATION 3-6 Manual 0-5054

3.07 Lift TIG (GTAW) Setup

Figure 3-3: Setup for Lift TIG (GTAW) Welding

Lift TIG Sequence of Operation

1. Switch the ON/OFF Switch (located on the rear panel)

to OFF.

2. Connect the earth clamp to the Positive Output Terminal,

torch cable to the Negative Output Terminal and gas

hose to the output of an Argon regulator.

3. Plug the Power Source in and switch the power switch

ON.

4. Set the Process Selection Switch to Lift TIG.
5. Set the Weld Current control to the desired welding

current.

6. Switch the ON/OFF Switch to the ON position.

7. Commence welding. If necessary, readjust the Weld

Current control to obtain the welding condition re-

quired.

8. After completion of welding the Power Source should

be left turned ON for 2 to 3 minutes. This allows the

fan to run and cool the internal components.

9. Switch the ON/OFF Switch (located on the rear panel)

to the OFF.

Set Welding Current

as Specified by the

Electrode Manufacturer

Set Process Selection

Switch to LIFT TIG

Positive Output Terminal

(Dinse™ 50)

Negative Output Terminal

(Dinse™ 50)

Art #: A-08470_AB

Secure the gas cylinder in an

upright position by chaining them

to a stationary support to prevent

falling or tipping