Using the Fryer for the First Time

Before lighting the pilot, fill the frypot with frying compound.

Then light the pilot according to the instructions inside

the fryer compartment on the inner panel. If you are using

a cooking oil, you may now turn the main burner on by

turning the knob on the automatic gas valve. If you use a

hydrogenated (solid) frying compound, it is wise to melt it in

a stock pot on the range before putting it in the fryer. If this

is not done, pack the frypot with the compound and turn the

main burner on for a few seconds and turn it off for a few. See

the lighting and shut-down instructions for “How to turn on

the main burner once the pilot is lighted.”

Intervals of about three seconds on and ten seconds off are

about right. Keep doing this until the shortening is melted.

If any smoke is seen during this process, you are heating

too fast and scorching the shortening, thus cutting down

its useful life and possible damaging the frypot. Shortening

level must cover the thermostat bulbs when fryer is in

operation.

After turning the main burner on, set the thermostat at 325°

to check calibration of the thermostat. Let the burner cycle

at least four times and suspend a deep fat fryer thermometer

in the middle of the frypot about 3” deep. When the burner

just comes on after the fourth cycle, the reading on the

thermostat should agree with the thermostat setting. If not,

calibrate the thermostat according to the instructions in the

Cleaning and Maintenance Section of this manual.

OPERATION

INSTALLATION Continued

Radiation Shield

This radiation shield must be in place when fryer is installed

in other than fire resistive locations.

IMPORTANT: The flue riser must be installed within the back

guard. This rectangular riser fits over the collar of the flue

collector box inside the fryer. Place the flue riser upright

through opening in the back top and slide over collar. (See

Figure 2.).

FLUE RISER

BACK ALUMINIZED

SIDES AND FRONT

HEAT SHIELD

FIGURE 2

RADIATION SHIELD

REMOVE EXISTING

#10 SHEET METAL

SCREWS (2 REQ'D)

FROM HIGH SHELF OR

BACKGUARD TO INSTALL

RADIATION SHIELD

FIGURE 1

METHOD OF ATTACHING RADIATION SHIELD TO

BACKGUARD OR HIGH SHELF

Advertising
Ce manuel est liée aux produits suivants: