Procedure for aluminum terminations – GE Industrial Solutions Spectra Series Power Panelboards AMC6FGB or AMC4FGB Manuel d'utilisation

Page 3

Advertising
background image

3

Figure 7. Installation of the center barrier with two breakers.

Figure 7. Installation de la barrière du centre avec deux disjoncteurs.

Figure 9. Attaching the breaker module to the rail.

Figure 9. Attacher le module de disjoncteur au rail.

Procedure for Aluminum

Terminations

1. Strip the insulation, being careful to not nick the

wire.

2. Clean the wire strands with a wire brush.
3. Thoroughly coat the stripped conductor with a

suitable antioxidant compound, such as ALNOX or

PENETROX A13.

4. Insert the conductor and tighten the connector screw

to the torque indicated on the rating label.

Figure 8. Completed installation with two breakers.

Figure 8. Installation complétée avec deux disjoncteurs.

5. Installer le module. Rétracter complètement les

loquets et accrocher un côté du module de

disjoncteur au rail de l’intérieur, tel que montré à la

Figure 9. Relâcher le loquet. Pivoter le module sur les

barres omnibus et engager le second loquet.

Relâcher le loquet. Serrer les vis de loquet à 25 lb.-po,

tel que montré aux Figures 9 et 10.

Figure 10. Securing the module to the interior.

Figure 10. Fixer le module à l’intérieur.

6. Installer les cosses sur les extrémités charge du

disjoncteur. Utiliser le kit de pièces de cosses numéro

FCALK218H pour les disjoncteurs deux-bornes et

FCALK318H pour les disjoncteurs trois-bornes.

Center Barrier

Barrière du Centre

Thread-Cutting

Screws

Vis auto-

taraudeuses

Latch

Loquet

Latch Screw

Vis du loquet

Latch Screw

Vis du loquet

Advertising