4.2.1 HORIZONTAL AIR TERMINAL INSTALLATION

A.

Stretch the inner fl ex pipe to the required length
taking into account the additional length needed for
the fi nished wall surface. Apply a heavy bead of the
high temperature sealant W573-0007 Mill Pac (not
supplied) to the inner sleeve of the air terminal. Slip
the vent pipe a minimum of 2” (50.8mm) over the inner
sleeve of the air terminal and secure with 3 #8 screws.

B.

Using the outer fl ex pipe, slide over the outer
combustion air sleeve of the air terminal and
secure with 3 #8 screws. Seal using high
temperature sealant W573-0002 (not supplied).

C.

Insert the vent pipes through the fi restop
maintaining the required clearance to
combustibles. Holding the air terminal (lettering
in an upright, readable position), secure to the
exterior wall and make weather tight by sealing
with caulking (not supplied).

D.

If more vent pipe needs to be used to reach
the appliance, couple them together as
illustrated. The vent system must be supported
approximately every 3 feet (0.9m) for both vertical and horizontal
runs. Use noncombustible strapping to maintain the minimum
clearance to combustibles.

The air terminal mounting plate may be recessed into the exterior wall
or siding no greater than the depth of its return fl ange.

E.

The vent heat shield must be installed only when terminating
horizontally. Remove the two screws nearest the vent collars on
the top of the appliance. Align the vent heat shield (supplied) and
secure. Adjust the vent heat shield to touch the fi restop spacer.

23.5B

HI-TEMP

SEALANT

#8 X 1/2” SELF DRILLING

SCREWS & WASHERS

INNER COUPLER

OUTER COUPLER

OUTER

FLEX PIPE

INNER
FLEX PIPE

OUTER

FLEX PIPE

SCREWS

#10x2"

2" (50.8mm) OVERLAP

OUTER FLEX PIPE

INNER FLEX

PIPE

HIGH TEMPERATURE

SEALANT

CAULKING

VENT
HEAT

SHIELD

SCREWS

Advertising