INSTALLATION PROCEDURES

16

Manual 0-2654

2. Feed the Slave Power Supply pilot lead through

the boot at the end of the Arc Starter Box.

3. Connect the pilot lead to the pilot connection per

the following procedure:

a. Remove the nut and external star washer from

the pilot connection bolt.

NOTE

Make sure that the inner nut is stays tight.

b. Place the ring lug on the pilot wire over the

end of the bolt.

c. Re-install the external star washer and nut to

secure the lead.

Star

Washer

Nut

Pilot Lead

Connection

Slave Pilot Lead

A-01782

Figure 3-15 Pilot Lead Connection - Slave

4. Feed the Slave Power Supply power lead through

the boot at the end of the Arc Starter Box.

5. Connect the power lead to the buss bar per the

following procedure:

a. Remove the nut and washer from the upper

bolt.

b. Remove the bolt and washer from the upper

hole of the buss bar.

c. Place the ring lug on the power lead over the

end of the bolt.

d. Re-install the bolt and washer with the lug

into the upper hole of the buss bar.

e. Re-install the nut and washer to secure the

lead.

A-01783

Washer

Slave Power

Lead

Buss Bar

Bolt

Nut

Washer

Figure 3-16 Power Lead Connection - Slave

6. Connect the other end of the Pilot Lead, two wires,

to the Slave Power Supply per the following pro-
cedure:

a. Remove the right side panel from the Slave

Power Supply.

b. Feed the Pilot Lead, two wires, through the

small strain relief at the front panel of the Slave
Power Supply.

c. Remove the nut and star washer on the ground

terminal of the pilot connection inside the
power supply.

Small Strain

Relief

Black Wire

of Pilot Lead

Ground Terminal

Nut

Star Washer

Pilot Terminal

Red Wire

of Pilot Lead

A-01536

Figure 3-17 Pilot Lead Connection at Slave Power