Installation Instructions

C5

Check for Leaks

Check for leaks. After connecting the cooktop
to gas, check system for leaks with a
manometer. If a manometer is not available,
turn the gas supply on to the cooktop and
use a liquid leak detector at all joints and
connections to check for leaks. Tighten all
connections if necessary to prevent gas
leakage in the cooktop or supply line. Check
alignment of valves after connecting the
cooktop to the gas supply to be sure the
manifold pipe has not been moved. A
misalignment could cause the valve knob
stem to rub on the control panel, resulting
in a gas leak at the valve.

DO NOT USE OPEN FLAME TO CHECK
FOR LEAKS!

Disconnect this cooktop and its individual
shutoff valve
from the gas supply piping
system during any pressure testing of that
system at test pressures greater than 1/2" psig.
Isolate the cooktop from the gas supply piping
system by closing its individual shutoff valve
during any pressure testing of the gas supply
system at test pressures equal to or less than
1/2" psig.

INSTALLATION OVER
BUILT-IN OVEN

See built-in oven installation for complete
installation instructions.

90

°

STREET EL

CABINET SIDES

2" DIA. HOLE (20 7/8"

FROM FRONT OF

COUNTERTOP TO

HOLE CENTER)

5" TO CENTER

OF 2" DIA. HOLE

FROM COUNTERTOP

C6

Installing the Cooktop

cont.