Rating Plate

When corresponding with the factory or your local

authorized factory service center regarding service problems

or replacement parts, be sure to refer to the particular unit

by the correct model number (including the prefix and

suffix letters and numbers) and the warranty serial number.

The rating plate affixed to the rear of the oven contains this

information.

Clearances and Setting

Minimum Clearance for Installation .

Combustible to Non-Combustible Wall Clearance:

Side:

1” (25 mm)

Rear:

1” (25 mm)

Proper placement of the oven will ensure operator

convenience and satisfactory performance.

NOTE: Adequate clearance must be provided for servicing

and proper operation.

Location

Due to the heat a counter-top oven may produce, it must

be placed on a non-combustible surface. Do not store

combustible materials on top of any oven.

Electrical Connections

An all pole disconnect must be provided by the installer.

Make sure electrical supply corresponds with that specified

on the rating plate located in the rear of the oven.

Leg Instillation

Optional legs – for shipping purposes the optional 4” (102

mm) legs are not mounted to any of the ovens.

1. After unpacking, remove legs, baking decks and any

other material from inside the oven.

2. Place the unit on a counter or other flat surface.

3. With sufficient help, tilt unit carefully onto its back.

4. Screw legs into the bottom of the unit using holes

provided and tighten with an adjustable wrench.

5. Carefully tilt oven up onto the legs and adjust the bottom

of the legs to make the unit level.

6. Slide baking deck into each shelf and secure with

stainless steel hearth trim. (See Deck Installation)

Deck Installation

A. Slide baking decks into each shelf.

B. Remove screw from mounting bracket left and right side.

C. Place stainless steel (deck hold down) in place.

D. Fasten screws to mounting bracket.

MOUNTING

SCREW

LOCATION

DECK

DECK HOLD DOWN

Initial Start Up

After the electrical connections have been made, the oven

will need approximately 2 to 3 hours to burn off. Initial

heating of the oven may generate smoke or fumes and must

be done in a well-ventilated area.

CAUTION: Over-exposure to smoke or fumes may cause

nausea and dizziness .

For initial heating of the oven, follow the steps below:

A. Place the oven in a well-ventilated area.

B. Open the door and remove any instructions or samples

that have been shipped with the unit.