IMPORTANT: If any original wire has to be replaced, it must be replaced with type 105° C or its equivalent.
Terminal Block on 85 Models only.

RED

BLACK

YELLOW

YELLOW

YELLOW

BLUE

RED

HIGH TENSION

INSIDE
FURNACE

+ 12V DC

NEG

RED

YELLOW

ELECTRODE

VALVE

RED

1

4

2

5

3

6

1

4

2

5

3

6

+THERMO

MOTOR

CIRCUIT

BREAKER

IGNITION

CONTROL

BLW PWR

SAIL

SWITCH

WHITE

LIMIT

SWITCH

WHITE

BLUE

BLUE

YELLOW

RED

GROUND

BLUE

THERMOSTAT

ON

OFF

ON/OFF

SWITCH

THERMO

14

CUSTOMER SUPPLIED WIRING

12V DC
SUPPLY

5

4. Secure furnace to coach floor with four screws.

LOCATE SCREWS TO

AVOID DAMAGE TO ANY WORKING COMPONENTS

,

WHILE MAINTAINING PRESSURE

SEAL AGAINST GASKET ON SCREEN

.

CUTOUT

RECOMMENDED WALL THICKNESS

1-1/2˝ - 2-1/2˝

DO NOT OVERSIZE HOLE

-

OVERSIZING CAN RESULT IN WATER LEAKAGE

EXTERIOR WALL CUTOUT

A

B

RECESS FURNACE

(

FIG

13

)

4-3/4˝

5. Place recess cover over top of furnace with all edges of door outside

of control box. Hold firmly into place while using holes in door to
locate mounting tabs and clips. Use #8 or #10 sheet metal screws to
fasten door in place.

Follow

STANDARD FURNACE INSTALLATION

instructions for ducting, thermo-

stat and draft cap assembly.

SYSTEM CHECKS

ƽ

WARNING

FIRE OR EXPLOSION

Never check for leaks with an open flame.

PROPANE GAS PRESSURE TEST

The furnace and any individual shut-off valve must be disconnected
from gas supply piping system during any pressure testing of system
at test pressures of more than 1/2 PSI.

Before furnace is connected piping systems must be tested to be leak
free. The test must maintain air pressure of at least 6˝ of mercury or 3
PSI for at least 10 minutes.

The entire piping system must be maintained within a range of 10-14˝
W.C. when all appliances are in operation. Test gas connections for
leakage with a leak test solution.

STATIC PRESSURE TEST

(

FIG

.

1)

Please refer to Engineering Addendum when installing the furnace. This
will provide you with allowable maximum case static pressures with
each possible variation of duct configurations. The addendum is avail-
able from your Atwood Field Service Representative or by calling
Atwood Service Toll Free.

Reducing the number of duct turns and stretching the ducts will
increase airflow and reduce static pressure. Adding ducts or increasing
the discharge (hard duct) system will also reduce static pressure.

You must follow the manufacturer’s recommendations and specifica-
tions for optimum performance and proper operation.

DIAGNOSTIC CHART

FAULT

LED INDICATION

Internal Circuit Board Failure

Steady on, no flashing

Limit switch/Airflow problems

1 flash with 3-second pause

Flame Sense Fault

2 flashes with 3-second pause

Ignition Lockout Fault

3 flashes with 3-second pause

Note: On/OFF Switch may be separate

or combined with Circuit Breaker.